Speed Governors for Turbines

The speed governor keeps the turbine at the required speed during start-up, under load and in grid frequency regulation, by commanding the admission of steam, gas or water through an actuator and a valve. The system usually also includes a separate overspeed protection channel, which trips the machine when normal control can no longer limit acceleration. The right choice depends on the type of turbine, the existing actuator and the operating regime of the unit.

A modern governor measures speed with two or three magnetic sensors mounted at a toothed wheel on the shaft, compares the value with the reference and corrects the valve position through a PID-type algorithm. The output commands an electrohydraulic or electric actuator, and the loop is closed through the servomotor's position transducer. Usual functions are automatic start-up with a speed ramp, fast passage through critical speeds, synchronisation with the grid and droop, which shares the load between several units connected in parallel.

Turbines are grouped by their control behaviour: a unit supplying an isolated network operates in isochronous mode, while one connected to the national system operates with droop. The performance classes of steam turbine governors are described in NEMA SM 23. Many operators replace old mechanical-hydraulic governors with digital equipment, keeping the existing servomotor; the compatibility of the interface with it decides whether the job stays simple or becomes a full project. On every job of this type the signals to the control system are also checked, because a change in the trip logic requires testing before return to service.

How to choose

Turbine and fuel type

Steam, gas and hydraulic turbines have different dynamics; the algorithm and the actuator's response times must be matched to the rotor inertia and to the volume of steam or gas between the valve and the turbine.

Operating regime

State whether the unit operates in isolation, in parallel with the grid or in both modes; the governor must allow switching between isochronous and droop without load shocks.

Interface with the actuator

Check whether the existing actuator is driven by current, by voltage or through a servo valve, and whether the new governor can deliver the same type of signal, with the same polarity and range.

Speed measurement redundancy

Two sensors with voting, or three with median value selection, avoid a false trip when a single pickup fails; the mounting distance from the toothed wheel also matters.

Independent overspeed protection

The trip channel must operate separately from the control loop and be testable in service, without bringing the turbine to the actual trip speed.

Communication with the control system

Choose the protocol used by the control room, for example Modbus or Profibus, and the number of hard-wired signals needed for the emergency trip.

Required integrity level

If the trip function is part of a safety instrumented system, the equipment must have the documentation required by IEC 61508 or IEC 61511.

What to send for a quotation

  • The turbine type and rated power
  • The code of the existing governor or actuator, from the nameplate
  • The operating regime: isolated, in parallel with the grid or both
  • The type and range of the control signal to the valve
  • The communication protocol required by the control system
  • The quantity and the desired deadline, for example for a planned shutdown

Typical applications

  • Steam turbines in thermal power plants
  • Gas turbines for generation and drive
  • Small and medium hydropower plants
  • Compressor and process pump drives

Maintenance and spare parts

Magnetic speed sensors lose their signal through fouling or displacement relative to the toothed wheel, so the mounting distance is checked at every shutdown. Electrohydraulic actuators need clean oil, and the filters and servo valves are monitored according to whether the oil meets the required cleanliness class. The overspeed trip test is scheduled periodically, following the machine procedure, and the governor parameters are saved before any change.

Brands we quote for this product type

Frequently asked questions

What is the difference between the speed governor and the overspeed trip system?

The governor acts continuously on the admission valve and keeps the speed around the operating value. The overspeed trip system is a separate protection level, which comes into action only when the speed exceeds a threshold, quickly closing the safety valves. The two must be independent in sensors, circuits and logic, because a governor fault must not also disable the protection. Thresholds are set according to the turbine documentation.

Can I replace an old hydraulic governor with a digital one without changing the servomotor?

Often yes, provided the interface is compatible: the type of signal to the servo valve, the position feedback and the stroke times of the servomotor. The digital governor adapts through parameters, but cannot compensate for a worn servomotor or one with mechanical play. Before ordering, check the condition of the servomotor and the mechanical linkages, because they limit the quality of the control.

What data do I send for a quotation on a speed governor, and how long does delivery take?

Send the code from the existing governor or actuator, the turbine type and power, the operating regime, the type of signal to the valve and the communication protocol desired. A photo of the nameplate speeds up identification. Delivery is 24–72 h when the item is in stock, locally or at the supplier, or to order, usually 1–4 weeks; depending on brand and specification it can take longer.

Why are three speed sensors used instead of one?

A single sensor makes speed a single point of failure: if the signal disappears, the governor may interpret the loss as a stop or, conversely, command the valve to open. With three sensors and two-out-of-three voting, the machine stays in operation when one fails, and the fault is signalled for repair at the first shutdown. For large turbines, the additional cost is small compared with the loss caused by a false trip.