The bushing carries a high-voltage conductor through the tank of a transformer or through a building wall, keeping insulation from earth. Current and voltage instrument transformers reduce network values to standardised quantities that protection relays and meters can read safely. They are substation parts that are changed rarely, but whose failure takes a whole circuit out of service.

A bushing has a central conductor surrounded by insulation, usually with condenser-type field grading layers, and a flange fixed to the transformer tank or to the wall. The insulation can be oil-impregnated paper (OIP), resin-impregnated paper (RIP) or a synthetic resin-impregnated variant, and the outer shed is porcelain or silicone composite. The capacitive test tap allows periodic checking of capacitance and dielectric loss factor (tan δ), which track the ageing of the insulation. The basic requirements are in the IEC 60137 series.

Instrument transformers are divided into current transformers (CT) and voltage transformers (VT), with requirements set in the IEC 61869 series. Current transformers have separate cores for measurement, where the accuracy class matters, and for protection, where behaviour at high fault currents and the risk of saturation matter. At very high voltages, capacitor voltage transformers are frequently used, with a capacitive divider and an intermediate electromagnetic unit, which can also serve for coupling communication signals onto the line. The internal insulation can be oil, SF6 gas or, at lower voltages, cast resin.

How to choose

Rated voltage and insulation level

The highest voltage for equipment and the impulse and power-frequency withstand levels must match your network, with correction for altitude if the substation is above 1,000 m.

Rated current and short-time current

The continuous current and the thermal short-circuit current, with its value and duration, are taken from the substation calculations, not from the old type you are replacing.

Insulation type and mounting position

OIP, RIP and synthetic variants differ in sensitivity to moisture and in fire risk; the angle of inclination from the vertical must be specified, especially for transformer bushings.

Accuracy class and rated burden

Measuring classes (for example 0.2 or 0.5) and protection classes (for example 5P or 10P) are chosen according to the connected devices; the actual burden, cable plus relays, must not exceed the rated burden in VA.

Accuracy limit factor and saturation

A current transformer that saturates at fault current can delay tripping; for fast protections, discuss the limit factor or the transient classes, of TPY type, with the designer.

Creepage distance and pollution level

The specific creepage distance is chosen according to the pollution level of the site, per IEC 60815; industrial, coastal or salt-fog areas require higher values.

Mounting dimensions for replacement

The flange, the length of the part immersed in oil and the terminals must match the existing equipment; the rating plate or a drawing with dimensions greatly shortens identification.

What to send for a quotation

  • Rated voltage, insulation level and site altitude
  • Rated current and short-circuit current, with its duration
  • Product type: bushing, CT, inductive VT or capacitor VT
  • For CT and VT: transformation ratios, accuracy classes and burdens
  • Rating plate of the equipment being replaced or the drawing with mounting dimensions
  • Pollution level of the site and quantity required

Typical applications

  • Power transformers in substations
  • Gas-insulated substations (GIS)
  • Connection of generators to the grid
  • Metering and line protection

Maintenance and spare parts

Bushings are monitored by periodic measurement of capacitance and loss factor at the test tap, by thermography on terminals and by checking the oil level, where an indicator exists. A deviation from the commissioning values calls for further analysis. The shed is cleaned in areas with pollution deposits. For instrument transformers, tightness, oil level or gas pressure are checked and, at set intervals, ratio and accuracy. The secondary of a current transformer is never left open under load.

Brands we quote for this product type

Frequently asked questions

Why is the loss factor (tan δ) measured on a bushing?

The insulation of a bushing with grading layers behaves like a capacitor, and the losses in it grow with moisture, ageing and degradation of the paper. Measuring capacitance and tan δ at the test tap, repeated at regular intervals and compared with the initial values, shows the trend without removing the bushing from the transformer. A jump in capacitance can indicate a punctured layer, and an increase in losses, moisture or ageing.

What is the difference between an inductive and a capacitor voltage transformer?

The inductive one has a core and two windings, like an ordinary transformer, and is used as a rule at medium voltages and at some high voltages. The capacitor one first reduces the voltage through a capacitor divider and then through an electromagnetic unit, which makes it more economical at very high voltages. In addition, the capacitor can serve for coupling communication signals onto the line. The transient response of the capacitor type should be discussed with the protection designer.

Why must the secondary of a current transformer not be left open?

A current transformer works as a current source: if the secondary is open, the primary current magnetises the core to saturation and very high voltages appear in the winding, dangerous for personnel and for the insulation. For this reason the circuits are short-circuited with a test terminal or a jumper before any work on the connected devices. The same rule applies to maintenance work in relay panels and on meters.

What do I send for a quotation on bushings or instrument transformers and how long does delivery take?

Send the rated voltage, the current, the product type, the accuracy classes and the burdens for instrument transformers, plus the rating plate of the equipment being replaced or the drawing with dimensions. The lead time is 24–72 h when the item is in stock, locally or at the supplier; otherwise it is brought in to order, usually 1–4 weeks, and depending on the brand and the specification it may take longer.