PLCs and Controllers
A PLC (programmable logic controller) is a rugged industrial computer, programmed to read signals from sensors and automatically control motors, valves or other equipment according to a logic defined by the user. It is used on production lines, in industrial HVAC systems and in chemical process control, wherever reliable, repeatable automation is needed without constant manual intervention.
A PLC has a central processing unit, digital and analogue input/output modules (expandable for larger processes) and a power supply, all mounted on a DIN rail in an electrical cabinet. Programming is done in standardised languages (ladder, function block diagram, structured text according to IEC 61131-3), and communication with other equipment or with a SCADA system is done through industrial protocols such as Modbus, Profinet or Ethernet/IP.
A PLC suitable for industrial applications has a scan time fast enough for the controlled process, enough memory for the program and data required, and a protection rating suited to the environment (dust, humidity, vibration). The long-term availability of compatible expansion modules also matters, as does ease of integration with an existing HMI or SCADA system, to avoid being locked into a single software supplier.
How to choose
Number and type of inputs/outputs required
All the sensors and actuators to be connected are counted, digital and analogue, with a margin for future expansion; a PLC chosen strictly at the current limit becomes insufficient at the first process change.
Processing power and scan time
Fast processes (packaging, motion control) require a short scan time and a high-performance processor; slow processes (HVAC, dosing) can work well on a mid-range PLC.
Communication protocols required
Compatibility with Modbus, Profinet, Ethernet/IP or other protocols must be checked against the existing equipment (HMI, drives, smart sensors), not only against the requirements of the new project.
Installation environment (temperature, dust, vibration)
An air-conditioned cabinet allows a standard PLC, but mounting directly in the hall, with dust or vibration, calls for enclosures and modules with a high protection rating or ruggedised industrial variants.
Programming software and long-term maintenance
Some platforms require costly programming licences or licences tied to a single manufacturer; check the availability of engineers or integrators familiar with the chosen platform, for future maintenance.
Possibility of later expansion
A modular system, with an expandable rack and additional I/O modules available, allows the process to grow without completely replacing the original automation.
What to send for a quotation
- The number and type of inputs/outputs required, digital and analogue
- The communication protocols required (Modbus, Profinet, Ethernet/IP) and the existing equipment to be connected
- A short description of the process to be automated and the speed requirements (scan time)
- The mounting environment (air-conditioned cabinet or directly in the hall, dust, vibration)
- Whether an HMI is needed or a connection to an existing SCADA system
- The preferred software platform or the equipment already used in the plant, if any
Typical applications
- Production lines
- Industrial HVAC systems
- Materials processing
- Chemical process control
Maintenance and spare parts
The components that fail most often are the power supplies, the memory backup battery and the contacts of the input/output modules subject to repeated stress. Periodic checking of the tightness of connections in the cabinet is recommended, along with saving a copy of the program at every change and testing the backup battery, whose discharge can erase process data at an unexpected shutdown.
Brands we quote for this product type
- akYtec
- Allen-Bradley
- B&R
- Bachmann electronic
- Baumüller
- Beckhoff
- Beijer Electronics
- Beijing Sifang Automation
- Brainchild Electronic
- CAREL
- CCC – Compressor Controls Corporation
- Datakom
- DEIF
- Eckelmann
- Elap
- Eliwell
- ELREHA
- Emko Elektronik
- Energy Control Technologies (ECT)
- Fatek Automation
- HD Hyundai Robotics
- HIMA
- Hitachi Industrial Equipment Systems
- HollySys
- Horner Automation
- ICP DAS
- IDEC Corporation
- Inovance
- Maple Systems
- MEGMEET
- Mitsubishi Electric
- Omron
- Opto 22
- Panasonic Industry
- Phoenix Contact
- Pilz
- Pixsys
- Red Lion Controls
- Regin
- RESOL
- Rockwell Automation
- Schneider Electric
- Selectron Systems
- Seneca
- Siemens
- SIGMATEK
- Smar
- SUPCON
- Syntec
- Unitronics
- Wago
- Woodward
- Xinje
Frequently asked questions
What is the difference between PLCs and a SCADA system?
The PLC executes the control logic directly on the machine, in real time, reading sensors and controlling actuators according to a program. The SCADA system is the supervisory layer above it, which collects data from one or more PLCs, displays it to the operator and allows remote commands, but does not replace the local control logic.
How are PLCs and controllers chosen correctly for a new production line?
The starting point is the exact number of inputs and outputs required, with an expansion margin, and the communication protocols required by the existing equipment. The speed requirements of the process and the mounting environment are added, then it is checked whether the chosen software platform has local support for programming and maintenance.
What should be sent for a PLC quotation, and how long does delivery take?
The number and type of inputs/outputs, the communication protocols and a short description of the process to be automated are needed. Delivery is to order, typically 1–4 weeks, depending on the manufacturer, and faster if the model chosen is from the supplier's standard range.
Can a new PLC be integrated with older sensors and drives in the plant?
Usually yes, if the old equipment communicates through standard protocols (Modbus, 4-20 mA signal) or has conventional digital/analogue outputs. Integrating very old equipment without a digital protocol may require additional conversion modules, which should be discussed before choosing the PLC.